Bangladesh joins nuclear power club as Rooppur sends first 350MW to national grid

Bangladesh has taken a major step towards nuclear power generation after the first unit of the Rooppur Nuclear Power Plant successfully connected to the national grid, delivering an initial 350 megawatts (MW) of electricity during a trial run on Tuesday.

Science and Technology Minister Fakir Mahbub Anam announced the milestone while briefing journalists outside the plant in Ishwardi, Pabna, saying the successful grid synchronisation marked Bangladesh’s emergence as the world’s 33rd nuclear power-producing country.

The first electricity from the Russian-built plant was fed into the national grid at 3pm, in the presence of the minister. Output reached a maximum of 350MW before being reduced to 300MW to maintain grid stability.

“This is an extremely encouraging development for the country,” the minister said, adding that the achievement followed years of work, technical preparations and a series of complex tests.

He also said representatives of the International Atomic Energy Agency (IAEA) had expressed satisfaction with the project’s overall progress and safety arrangements, helping pave the way for the successful synchronisation.

Prime Minister Tarique Rahman and all those involved in the project were congratulated on the achievement, the minister added.

Project director Dr Md Kabir Hossain said electricity would initially be supplied to the national grid for around eight to 10 hours as engineers assess the performance of the plant’s turbine, generator and integrated operating systems.

The plant will then be disconnected from the grid for further technical tests. After an interval of approximately 28 hours, it is expected to reconnect for another four to six hours to complete additional operational and technical assessments.

Engineers will closely monitor the performance of individual systems, turbine and generator operations, and the stability of the connection with the national grid during each phase.

Once the required tests have been completed satisfactorily, the project will need further approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) before proceeding to the next stage of trial operations.

Under the agreement with the Russian contractor, the first unit must undergo a 10-month trial operation before it can begin permanent commercial electricity supply at full capacity.

Following completion of the process, the Bangladesh Atomic Energy Commission will provisionally take over the first unit from the Russian contractor. The Nuclear Power Plant Company Bangladesh Limited (NPCBL) will subsequently assume operational responsibility following a government notification.

The Rooppur project, located in Ishwardi in north-western Bangladesh, comprises two reactors, each with an installed capacity of 1,200MW, giving the plant a combined capacity of 2,400MW.

Once fully operational, the facility is expected to make a significant contribution to meeting Bangladesh’s growing electricity demand, diversifying its energy mix and strengthening long-term energy security.

The successful grid connection marks a transition from construction and commissioning towards electricity generation, although further regulatory approvals and extensive testing remain before commercial operation can begin.

The Nuclear Power Plant Company Bangladesh Limited (NPCBL), a state-owned company, is responsible for operating the facility.

The project was originally scheduled for completion in December 2025, but its deadline has been extended twice, with the latest timeline set for June 2028.

The extensions have not increased the approved project cost under the contractual arrangements. However, the depreciation of the taka against the US dollar has raised the project’s expenditure in local currency by around Tk26,000 crore, taking the estimated total to Tk1,38,686 crore.

Rooppur is the country’s largest single development project. Its two units are expected to add 2,400MW of nuclear-generated electricity to the national grid, providing a major new source of power as Bangladesh seeks to diversify its energy mix and reduce reliance on conventional fuel-based generation.

The briefing was attended by Rehan Asif Asad, adviser to the Prime Minister on science and technology affairs; Science and Technology Secretary Md Anwar Hossain; project director Dr Md Kabir Hossain; and NPCBL Managing Director Dr Zahidul Hasan, among other officials.