The government has approved fuel imports worth Tk8,010.14 crore to meet domestic demand for diesel, furnace oil and octane during the first half of 2027.
The four procurement proposals, placed by the Energy and Mineral Resources Division, were approved at a meeting of the Cabinet Committee on Government Purchase (CCGP) on Wednesday, chaired by Finance Minister Amir Khosru Mahmud Chowdhury.
Of the total, Tk2,405.38 crore will be spent on two consignments of diesel, Tk3,493.61 crore on high-sulphur furnace oil and Tk2,111.14 crore on octane.
Singapore-based Trafigura Pte Ltd has been recommended as the supplier for both diesel consignments and the furnace oil, while Unipac Singapore Pte Ltd has been recommended for the octane supply.
The first diesel consignment, under package PGC-03/1H2027, will cost an estimated Tk960.41 crore. The second, under package PGC-04/1H2027, has an estimated cost of Tk1,444.97 crore.
The furnace oil procurement, under package PGC-05/1H2027, involves an estimated Tk3,493.61 crore, while the octane import under package PGC-06/1H2027 will cost Tk2,111.14 crore.
The approvals form part of the government’s fuel-import plan for January-June 2027.
25-year power purchase tariffs approved for Payra, Rampal
In a separate decision, the CCGP approved 25-year tariff structures for electricity purchases from the 1,320MW Payra coal-fired power plant and the 1,320MW Maitree Super Thermal Power Project in Rampal.
The Bangladesh Power Development Board (BPDB) is expected to spend around Tk4.61 lakh crore to purchase electricity from the two plants over 25 years.
Of the amount, Tk2,28,663 crore will go to the Payra plant and Tk2,31,947 crore to the Rampal plant.
The approved tariff for Payra is Tk6.78 per kilowatt-hour. At this rate, the BPDB will pay around Tk9,147 crore annually. The tariff will be effective from December 8, 2020.
For Rampal, the tariff has been set at Tk9.11 per unit from the initial operation date until the commercial operation date, and Tk8.98 per unit thereafter. The BPDB will pay Tk5,104 crore for the initial period and around Tk9,227 crore annually after commercial operation begins.
The tariff approvals were sought to facilitate government subsidies for electricity purchases from the two plants. The Finance Division had earlier raised objections to providing the necessary subsidies because the tariff structures had not been approved by the government purchase committee.
The Payra plant, built by Bangladesh-China Power Company Ltd, began generating electricity in 2020. The Rampal project, developed by Bangladesh-India Friendship Power Company Ltd, started generation in 2024.
The approved tariff for Rampal will be effective from March 12, 2024.