HomeEnergyBAPEX spends just Tk14.60 lakh on Tk577cr rig project in 13 months

BAPEX spends just Tk14.60 lakh on Tk577cr rig project in 13 months

A Tk577.23 crore project to procure a 2,000-horsepower drilling rig for state-run BAPEX has fallen five months behind schedule, with the purchase contract still unsigned and expenditure barely reaching Tk14.60 lakh, or 0.03 percent of the project cost.

The delay persists despite completion of the tender evaluation, as Bangladesh Petroleum Exploration and Production Company Limited (BAPEX) is waiting for an opinion from Bangladesh University of Engineering and Technology (BUET) before proceeding with the contract.

The prolonged procurement process has raised concerns over whether the project can be completed within its March 2028 deadline.

The Implementation Monitoring and Evaluation Division (IMED) of the Planning Ministry flagged the slow progress at a review meeting on October 29.  

“It is an important project for upgrading the BAPEX, but its implementation is not proceeding according to the approved work plan. So, IMED has called for intensive monitoring to accelerate the project,” an IMED official, who attended the meeting, said.

According to the meeting minutes, the contract was scheduled to be signed on May 28, 2026, under the approved development project proposal (DPP).

The project started on October 1, 2025, with a completion deadline of March 31, 2028. By October this year, around 43 percent of its 30-month implementation period had elapsed, leaving just 17 months to complete the remaining work.

Financial progress stood at only 0.03 percent, against reported physical progress of 13 percent, including 2 percent in the current fiscal year. The review minutes, however, do not explain the wide gap between the two indicators.

BUET opinion holds up contract

The immediate bottleneck is the pending opinion from BUET.

After completing the technical and financial evaluation of bids, BAPEX placed the purchase proposal before the Cabinet Committee on Government Purchase. Following the committee’s decision, Petrobangla wrote to the BUET vice-chancellor on October 11, seeking the university’s opinion.

The IMED review noted that regular communication with BUET was continuing but did not specify when the opinion might be received.

As a result, the purchase remains stalled at the contract-signing stage, although the tender evaluation has been completed.

Tendering also ran behind schedule

The project encountered delays well before reaching the current impasse.

BAPEX’s board approved international tendering on October 12, 2025. The company sought permission from the Bangladesh Public Procurement Authority (BPPA) on November 17 to conduct the process offline under Rule 150 of the Public Procurement Rules 2025.

BPPA approved the request on November 23 but instructed BAPEX to use its standard PG5A tender document, which the authority published on December 23. BAPEX then prepared the tender papers and obtained legal vetting.

Consequently, the international tender was floated on January 28, 2026, nearly three months after the November 5, 2025 date stipulated in the DPP.

The submission deadline was subsequently extended twice at bidders’ requests, with bids finally opened on May 18.

Although 37 firms purchased tender documents, only five submitted bids. Of those, just two qualified in the technical evaluation and had their financial offers opened.

BAPEX’s board approved the technical and financial evaluation reports at its 523rd and 524th meetings in August.

IMED asks BAPEX to expedite work

At the October meeting, chaired by IMED head and Additional Secretary Md Saiful Islam, the participants unanimously directed BAPEX to obtain BUET’s opinion without further delay and remove administrative bottlenecks to expedite implementation.

“The company was also asked to intensify project activities and monitoring to ensure completion within the approved timeframe without compromising quality,” an IMED official said.

Other directives included complying with the Planning Division’s June 2022 development project guidelines, regularly updating implementation data in the electronic Project Management Information System (e-PMIS), completing the project audit and submitting evidence to IMED.

BAPEX was further instructed to hold regular meetings of the Project Implementation Committee and Project Steering Committee.

The project, implemented by BAPEX under Petrobangla and the Energy and Mineral Resources Division, comprises three procurement packages, two for goods and one for services.

IMED warned that the accumulated delays could make it difficult to complete the remaining work and achieve the project’s targets within the stipulated timeframe.