Elenga-Rangpur four-lane project to miss Dec deadline, stretching to 12yrs

The Elenga-Hatikamrul-Rangpur four-lane highway project is set to miss its December 2026 deadline as four construction packages are running behind schedule and need six more months to finish along with a mandatory one-year defect liability period.

The Roads and Highways Division has sought an 18-month extension to the key project until June 30, 2028, sending a proposal to the Planning Commission for approval. The extension, if granted, will stretch the Tk19,054-crore project to nearly 12 years since its launch in September 2016.

The extension proposal followed a Project Steering Committee meeting held in mid October chaired by Roads and Highways Secretary Mohammad Ziaul Haque.

“It appears that the full work of work packages 5, 13, 14 and 15 of the project will not be completed by December 2026. Although the preliminary work of the other packages can be finished within the DPP period, another six months are needed to complete the slow packages,” a Planning Commission official said.

“As per the contract terms, the contractor has to be given a one-year Defect Liability Period after the work is finished. That is, a total of 18 additional months are needed to complete the four packages, including the DLP,” he added.

Four packages lag behind

Officially known as the SASEC Road Connectivity Project-2, the project is being implemented by the Roads and Highways Department at an approved cost of Tk19,053.72 crore. The government is financing Tk7,857.92 crore, while the remaining Tk11,195.80 crore comes from an Asian Development Bank loan.

By the end of September, physical progress had reached around 92 percent, while financial progress stood at 85 percent.

Seven of the 11 construction packages, which received work orders in 2019, are expected to be completed within the existing deadline, according to the project director.

The remaining four packages — 5, 13, 14 and 15 — received work orders only in December 2021 and are now running behind schedule. They need approximately six additional months to complete construction.

The project director told the meeting that the additional construction time, together with the one-year defect liability period, made an 18-month extension necessary.

The Asian Development Bank’s loan agreement, however, runs until August 2027, nearly 10 months before the proposed project completion date.

The Economic Relations Division expressed no objection to the extension, while the Finance Division also agreed. The steering committee asked the Roads and Highways Division to submit the extension proposal with a detailed action plan to the Planning Commission.

Supervision contract needs another extension

The project’s construction supervision consultancy contract is also nearing expiry.

Signed on October 25, 2018, at Tk379.53 crore, the contract was initially scheduled to run until January 2023. It has since been extended twice without additional cost, most recently until December 31, 2026.

The meeting was told that the consultant’s workload had increased because additional items were incorporated into some construction packages to ensure quality and durability, while delays pushed back completion dates.

As construction will continue beyond the current contract period, the committee recommended a third extension through Addendum-3 to ensure continued supervision and quality control.

Salla residents demand underpass

Meanwhile, residents of Salla in Tangail have demanded an underpass under package 5, adding another issue for the project authorities to address.

The highway section passes through an area with connecting roads, a haat and bazaar, an Eidgah ground, a madrasa and primary and secondary schools on both sides. Residents need to cross the busy road regularly.

In October, locals blocked the road and formed a human chain demanding an underpass.

The project director told the meeting that the construction cost could be accommodated by adjusting the approved contract value of package 5.

The committee decided to form a technical team to inspect the site and submit recommendations. Depending on its findings, the Bridges Authority may be asked to take further steps.

It also stressed that the underpass issue should not hold up the overall project.