An 800-megawatt unit at Adani Power’s coal-fired power plant in Godda, Jharkhand, India, will be shut from midnight on Wednesday for 25 days of annual maintenance, with the unit expected to resume operation on December 18.
The shutdown is part of the plant’s scheduled maintenance programme, Adani Power said in a statement.
The work will include inspections, servicing of equipment and preventive maintenance. The company said it had obtained approval from the Bangladesh Power Development Board (BPDB) for the shutdown on October 26.
The plant’s other 800MW unit will continue operating normally, leaving half of its 1,600MW generating capacity unavailable during the maintenance period.
The temporary reduction comes as Bangladesh’s electricity demand has eased with the onset of winter, reducing the immediate pressure on power supplies.
According to hourly data from the BPDB, the country’s peak electricity demand was 12,423MW at 6pm on Tuesday. Adani’s plant supplied 901MW to Bangladesh’s grid at 7pm that day.
At 1pm on Wednesday, the plant was supplying 927MW, while total electricity supplied to the national grid stood at 10,985MW.
BPDB officials believe the shutdown of one unit is unlikely to disrupt supplies under current demand conditions. However, the situation could change if electricity consumption rises during the maintenance period.