Govt plans 3,295cr project to pave half of Dhaka division’s rural roads

The Local Government Engineering Department (LGED) has proposed a Tk 3,295-crore project to upgrade nearly half of the rural road network in Dhaka division, seeking to improve connectivity in the country’s rapidly expanding industrial and commercial belt.

The proposed ‘Important Rural Infrastructure Development Project–Dhaka Division’ aims to upgrade 30,326 kilometres of unpaved roads out of the 60,491km maintained by LGED across the division, according to the proposal, now under Planning Commission scrutiny for Ecnec approval.  

The LGED argues that the expansion of factories and commercial establishments in Gazipur, Narayanganj, Narsingdi, Manikganj, Munshiganj and Tangail has increased heavy-vehicle movement on rural roads that were not designed to carry such traffic.

Upgrading the roads is expected to facilitate the movement of agricultural and industrial goods, improve access to markets, support export-oriented businesses and generate employment.

LGED also expects the project to improve rural livelihoods, access to public services and connectivity to tourism-potential areas while supporting the protection of rivers and wetlands.

“Dhaka division is the hub of the country’s economic, administrative and industrial activities. Heavy vehicle movement has increased, creating additional pressure on the existing infrastructure,” said Kabir Ahmed, member of the Agriculture, Water Resources and Rural Institutions Division.

“If the project is implemented, a smooth, safe and uninterrupted communication system will develop across Dhaka division, ensuring quick marketing of industrial and agricultural products, while also creating new employment opportunities and playing an important role in earning foreign currency through the transport of exportable goods,” he added.

The proposed investment will be financed entirely from government funds, without foreign loans or grants. LGED initially planned to implement the project from October 2026 to March 2031. It has been included in the list of new, unapproved projects under the Annual Development Programme for fiscal year 2026-27.

In a recent meeting, however, the Planning Commission’s Project Evaluation Committee (PEC) has asked LGED to substantially revise the project design, cut several expenditure items, provide a clearer justification for road selection and ensure that the proposed works do not overlap with existing development schemes.

PEC orders spending cuts

The PEC meeting, chaired by Planning Commission Member Kabir Ahmed, examined the proposed expenditure and sought stronger justification for several budgetary allocations.

Representatives of the Finance Division, General Economics Division, Implementation Monitoring and Evaluation Division and Programming Division raised questions about the costs and called for comparisons with similar development projects.

The committee agreed to drop management expenses, seminar and conference costs, books and periodicals, security services, printing and feasibility studies.

It also recommended sharp reductions in several other allocations. Training expenditure was cut from Tk 10 crore to Tk 10 lakh, while outsourcing costs were reduced from Tk 42.56 crore to Tk 26 crore.

The publicity and advertising allocation was lowered from Tk 4 crore to Tk 1 crore, and consultancy costs were halved to Tk 1.5 crore. Fuel and lubricant expenditure was reduced from Tk 4 crore to Tk 50 lakh, while vehicle hire costs were cut from Tk 1.35 crore to Tk 80 lakh.

The committee also reduced the proposed purchase of motorcycles from 118 to 26, computers from 108 to 15 and laptops from two to one. Physical contingency was capped at 1 per cent and price contingency at 2 per cent.

The head of the Agriculture Division advised LGED to hire consultants only where essential, referring to an ECNEC decision on July 22 aimed at curbing consultancy expenditure in development projects.

Road selection, duplication under scrutiny

The PEC has asked LGED to provide a detailed picture of the existing road network in the project area, including total road length, paved and unpaved sections and roads already covered by other development schemes.

The revised proposal must separately identify union roads, upazila roads and routes intended only for maintenance. The committee stressed that the project must not duplicate road development activities under other LGED schemes in the same districts.

It also sought district-wise allocations and directed LGED to prepare cost estimates based on the standard schedule of rates. Procurement must comply with the Public Procurement Act 2006 and the Public Procurement Rules 2025.

Environmental safeguards and maintenance

The committee also sought a clearer environmental plan. The proposed plantation programme along 445 kilometres of roads is to be specified in terms of the number of saplings, with a target of 356,000 trees.

Species must be selected in consultation with the Ministry of Environment, Forest and Climate Change, taking local conditions into account. The PEC also recommended planting vetiver grass or similar vegetation along road slopes and bridge approaches to prevent erosion.

Relevant site and environmental clearances must be incorporated into the revised proposal.

The Rural Institutions and Coordination wing asked LGED to explain how the project would contribute to the government’s Fiscal Year Strategic Framework for Reform and Development (July 2026-June 2031) and the Sustainable Development Goals. The department must also estimate the direct and indirect employment opportunities expected from the project.

The General Economics Division called for a detailed maintenance plan to ensure the sustainability of roads and bridges after construction.

Implementation period revised

The PEC also examined the proposed implementation schedule. Government guidelines issued in June 2022 generally limit development projects to three years. Against this backdrop, the committee agreed to revise the proposed starting date from October to December 2026, retaining March 2031 as the completion deadline.

LGED must now incorporate the committee’s observations into the revised Development Project Proposal (DPP) and resubmit it to the Planning Commission for further appraisal and processing towards final approval through the prescribed government mechanism, including ECNEC where applicable.